Thursday, March 20, 2008

Agile for Consultant Development Teams

I'm a consultant (sounds like an admission at the start of a 12-step program). I love the Agile approach to software development but there seems to be a fundamental conundrum I haven't been able to solve -- software project pricing. Seems like my clients want to know, in advance, how much the development of software is going to cost (the nerve of some people!). I just can't see how to get a price together for a project using an approach that essentially leaves out the up-front design effort that is characteristic of the traditional waterfall approach. And the Agile experts with whom I've spoken have no answer to this either.

Now, I don't actually believe that the waterfall approach gives any better or more realistic cost estimate, except perhaps on the most simplistic of projects. If anything, I believe it is a more expensive method that produces a false sense of cost security. But, I'm not getting into a comparison of these approaches. I'm just trying to figure out how to give a customer a price for an Agile project. And I've tried to say things like "what is your budget? We'll do as many of your priorities as possible within that." There is a disconnect between what clients want to know (how much for the whole thing) and the reality of what the "whole" thing needs to be and how much it will really cost.

One approach would be to simply lie. Tall the client what they want to hear. And then manage the consequences in the middle of the project. Doesn't seem like the right way though.

So instead, we've been trying to educate our clients on the tension between cost and features. In essence,
We've been using a variation on Wide-Band-Delphi-Blind to create estimates. We take the full list of features, attempt to designate tasks for implementing them, and then send that around to as many senior developers as we can -- developers with the right skill set to create an estimate for that type of project. Each estimator does his estimate alone and sends the results back to a coordinator and then we go through the estimates collectively to resolve the differences. Using this estimate of all features we then attempt to explain to our client that the estimate is under their control -- choose high priority features to implement first and then work through the list until either features or budget are exhausted.

This is not too different from agile poker (http://www.planningpoker.com/). As I understand that technique, several estimators each make a bid for how long each task or feature will take. The actual bids are not really hours. They are units. After several rounds of bidding and discussion on differences between bids, the winning bids are turned into dollars by applying the development team's velocity to the bid and figuring out real hours. This means that we have to know that velocity -- not an easy problem in its own right.

But we end up in the same place -- with an estimate for the whole project which we then have to "sell" to the client. Is there a better way?

Thursday, November 15, 2007

Estimating Software Development

I'm an excellent software architect, developer, project manager, and even (as needed) sales person. But I can't estimate a project development effort to save my life. I waaay underestimate. Every time. I can lose money faster than a gambler in Las Vegas! So I figure I need to study the science (if such there is!) of estimating. In the past I've just thrown numbers into MS project and hoped for the best.

I was initially turned on to this idea of a systematic approach to estimating by one of the smarter folks I know, Norbert Winklereth, formerly of Omnimark and Stilo. He espouses an approach I had never heard of -- Wide Band Delphi Blind (WBDB). Being a believer in Agile methods, this appeals to me. I started reading up on it and I like what I see. It depends on several people looking at the whole problem (Wide Band), to develop a list of tasks and an estimate for each (The Oracle of Delphi) operating anonymously to reduce or eliminate political influence or pressure, (Blind). There's a fair writeup of it HERE.

There are a lot of parts to this, but the essence of it is to get several people working together to bring their collective expertise and experience to the issue of estimating an effort. And, it can be used to estimate a number of things, not just cost, but anything to which we can apply a unit of measure. One thing I began to see early on is that estimating the effort of a project and estimating the schedule are two completely different, though related things.

Then I read an article by Joel Spolsky (Joel on Software) on something he calls "Evidence Based Scheduling." Joel argues for (and, indeed, has a software product based on) creating schedules based on historical performance data (from time sheets or other records) combined with Monte-Carlo simultations. Again, recognizing the difference between effort and schedule, Joel makes a point that any task planned for more than 16 hours is not going to work and needs to be further factored. I think the same thing applies to estimating effort -- break it down into units of not more than 16 hours.

Another factor that Joel recognizes is the relative historical accuracy of an individual as an estimator - what he calls velocity, the ratio of an individual's estimate to the actual. A perfect estimator would always have a velocity of 1. A person's history of these ratios is his velocity history and is a factor in the Monte-Carlo simulation.

So, I'm thinking that a blend of these techniques may represent a reasonable estimating approach. We need to assemble a blind group, and a project leader who has and continues to build a velocity history for each blind participant. We need some Monte-Carlo simulation software, and maybe a tool to organize all this.

More to come